[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113539":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113539,787,2,"多选题","关于连续生产设备安装的测量，下列说法不正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","中心标板必须在浇灌基础时，配合土建埋设",true,{"key":16,"text":17,"correct":18},"B","设备安装平面线不少于纵、横两条",false,{"key":20,"text":21,"correct":14},"C","标高基准点埋设在设备底板下面的基础表面",{"key":23,"text":24,"correct":18},"D","独立设备安装的基准点采用简单的标高基准点",{"key":26,"text":27,"correct":18},"E","连续生产设备只能共用一条纵向基准线和一个预埋标高基准点","AC","2020版教材P24 本题考查的是机电工程中常见的工程测量。选项A，中心标板应在浇灌基础时，配合土建埋设，也可待基础养护期满后再埋设；选项C，标高基准点一般埋设在基础边缘且便于观测的位置。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]