[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113511":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113511,787,2,"多选题","危大工程实行分包并由分包单位编制专项施工方案的，专项施工方案实施前应经（ ）签字确认。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","总包单位技术负责人",true,{"key":16,"text":17,"correct":14},"B","相关专业承包单位技术负责人",{"key":19,"text":20,"correct":14},"C","项目总监理工程师",{"key":22,"text":23,"correct":24},"D","建设单位项目技术负责人",false,{"key":26,"text":27,"correct":24},"E","设计单位项目负责人","ABC","2020版教材P36 本题考查的是吊装方案选用。专项施工方案应当由施工单位技术负责人审核签字、加盖单位公章，并由总监理工程师审查签字、加盖执业印章后方可实施。危大工程实行分包并由分包单位编制专项施工方案的，专项施工方案应当由总承包单位技术负责人及分包单位技术负责人共同审核签字并加盖单位公章。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]