[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113493":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113493,787,2,"多选题","对于超过一定规模的危大工程，专家论证前专项施工方案应当通过（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工单位审核",true,{"key":16,"text":17,"correct":14},"B","总监理工程师审查",{"key":19,"text":20,"correct":21},"C","项目经理",false,{"key":23,"text":24,"correct":21},"D","项目部安全员",{"key":26,"text":27,"correct":21},"E","论证专家代表","AB","2020版教材P36 专家论证前专项施工方案应当通过施工单位审核和总监理工程师审查",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]