[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113421":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113421,787,2,"多选题","子分部工程可按（ ）进行划分。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","平面布置",false,{"key":16,"text":17,"correct":18},"B","材料种类",true,{"key":20,"text":21,"correct":18},"C","施工特点",{"key":23,"text":24,"correct":18},"D","施工程序",{"key":26,"text":27,"correct":18},"E","专业系统及类别","BCDE","本题考查的是建筑安装工程施工质量验收的项目划分和验收程序。当分部工程较大或者较复杂时，可按材料种类、施工特点、施工程序、专业系统及类别等划分为若干个分部工程。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]