[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113420":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113420,787,2,"多选题","建筑安装工程检验批主控项目有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对卫生.环境保护有较大影响的检验项目",false,{"key":16,"text":17,"correct":18},"B","确定该检验批主要性能的项目",true,{"key":20,"text":21,"correct":14},"C","无法定量采用定性的项目",{"key":23,"text":24,"correct":18},"D","管道的压力试验",{"key":26,"text":27,"correct":18},"E","保证安全和使用功能的重要检验项目","BDE","本题考查的是建筑安装工程施工质量验收的组织与合格规定。主控项目是保证工程安全和使用功能的重要检验项目，是对安全、卫生、环境保护和公共利益起决定性作用的检验项目，是确定该检验批主要性能的项目。例如：管道压力试验、电气的绝缘与接地测试等均是主控项目。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]