[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113418":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113418,787,2,"多选题","工业安装工程单位工程质量验收的参与人员包括（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设单位项目负责人",true,{"key":16,"text":17,"correct":14},"B","设计单位项目负责人",{"key":19,"text":20,"correct":14},"C","施工单位质量技术负责人",{"key":22,"text":23,"correct":24},"D","监理工程师",false,{"key":26,"text":27,"correct":24},"E","施工单位专业工程师","ABC","单位（子单位）工程的验收应在各分部工程验收合格的基础上，由施工单位（总承包单位）向监理（建设）单位提出报验申请，由建设单位项目负责人组织监理、设计、施工单位等项目负责人及质量技术负责人进行验收，并应填写验收记录。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]