[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113415":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113415,787,2,"多选题","单位工程完毕后，建设单位组织（ ）参加单位工程质量验收。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设备制造单位",false,{"key":16,"text":17,"correct":18},"B","施工单位",true,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":14},"D","材料供应单位",{"key":26,"text":27,"correct":18},"E","监理单位","BCE","本题考查的是工业安装工程施工质量验收的组织与合格规定。单位（子单位）工程的验收应在各分部工程验收合格的基础上，由施工单位（总承包单位）向监理（建设）单位提出报验申请，由建设单位项目负责人组织监理、设计 、施工单位等项目负责人及质量技术负责人进行验收，并应填写验收记录。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]