[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113410":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113410,787,2,"多选题","特种设备的开工告知方式有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","电话告知",false,{"key":16,"text":17,"correct":18},"B","电子邮件告知",true,{"key":20,"text":21,"correct":18},"C","网上告知",{"key":23,"text":24,"correct":18},"D","挂号邮寄",{"key":26,"text":27,"correct":18},"E","派人送达","BCDE","本题考查的是特种设备制造、安装改造及维修的规定。告知方式：施工单位可以采用派人送达、挂号邮寄或特快专递、网上告知、传真、电子邮件等方式进行安装改造维修告知。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]