[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113392":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113392,787,2,"多选题","项目成本控制的原则包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","成本最低化原则",true,{"key":16,"text":17,"correct":14},"B","全面成本控制原则",{"key":19,"text":20,"correct":21},"C","按实控制原则",false,{"key":23,"text":24,"correct":14},"D","动态控制原则",{"key":26,"text":27,"correct":14},"E","责权利相结合原则","ABDE","本题考查的是施工成本计划的实施。施工成本控制应遵循成本最低化原则、全面成本控制原则、动态控制原则、责权利相结合的原则。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]