[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113390":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113390,787,2,"多选题","下列属于项目施工成本控制方法的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","以施工图控制成本",true,{"key":16,"text":17,"correct":18},"B","以投标图控制成本",false,{"key":20,"text":21,"correct":14},"C","安装工程费的动态控制",{"key":23,"text":24,"correct":14},"D","工期成本的动态控制",{"key":26,"text":27,"correct":14},"E","施工成本偏差控制","ACDE","本题考查的是施工成本计划的实施。施工成本控制的方法：以施工图控制成本、安装工程费的动态控制、工期成本的动态控制、施工成本偏差控制。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]