[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113375":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113375,787,2,"多选题","检验试验计划的主要内容不包括（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同规定内容",true,{"key":16,"text":17,"correct":14},"B","设计图纸",{"key":19,"text":20,"correct":21},"C","质量要求",false,{"key":23,"text":24,"correct":14},"D","验收规范",{"key":26,"text":27,"correct":21},"E","执行标准","ABD","本题考查的是施工工序质量检验。选项A、选项B和选项D均为检验试验计划的编制依据，而主要内容则包括：检验试验项目名称；质量要求；检验方法；检验部位；检验记录名称或编号；何时进行检验；责任人；执行标准。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]