[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113374":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113374,787,2,"多选题","有关项目质量计划与施工组织设计、施工方案的联系和区别，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","性质相同",false,{"key":16,"text":17,"correct":18},"B","管理对象一致",true,{"key":20,"text":21,"correct":14},"C","目标不同",{"key":23,"text":24,"correct":18},"D","关注点不同",{"key":26,"text":27,"correct":18},"E","编制的依据和途径不同","BDE","本题考查的是施工质量预控。项目质量计划与施工组织设计、施工方案存在联系与区别：（1）联系：目标是一致的，均是确保项目工程的管理目标符合合同及相关法规的要求 ，符合项目策划的要求；管理的对象是一致的，即是同一个工程项目。（2）区别：性质不同，关注点不同，编制的内容不同，编制的依据不同，审批的途径不同，关注的相关方不同。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]