[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113372":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113372,787,2,"多选题","作业进度计划应该能够满足（ ）的施工顺序。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","先深后浅",true,{"key":16,"text":17,"correct":14},"B","先地下后地上",{"key":19,"text":20,"correct":14},"C","先干线后支线",{"key":22,"text":23,"correct":14},"D","先大件后小件",{"key":25,"text":26,"correct":27},"E","先支线后干线",false,"ABCD","本题考查的是作业进度计划要求。作业进度计划应具体体现施工顺序安排的合理性，即满足先地下后地上、先深后浅、先干线后支线、先大件后小件等的基本要求。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]