[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113370":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113370,787,2,"多选题","施工技术交底的依据包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目质量策划",true,{"key":16,"text":17,"correct":18},"B","进度计划",false,{"key":20,"text":21,"correct":18},"C","资源安排计划",{"key":23,"text":24,"correct":14},"D","施工组织设计",{"key":26,"text":27,"correct":14},"E","施工工艺","ADE","本题考查的是施工技术交底。施工技术交底的依据：项目质量策划、施工组织设计、专项施工方案、施工图纸、施工工艺及质量标准等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]