[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113369":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113369,787,2,"多选题","关于设计变更的说法，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计变更必须说明变更原因和产生的背景",true,{"key":16,"text":17,"correct":14},"B","未经建设单位同意的变更视为无效变更，施工单位不得执行",{"key":19,"text":20,"correct":14},"C","设计变更应按照变更后的图纸由原来的施工单位实施，监理工程师签署实施意见",{"key":22,"text":23,"correct":14},"D","重大设计变更应按照有关规定办理审批手续",{"key":25,"text":26,"correct":27},"E","设计变更由设计单位提出，施工单位不能提出设计变更",false,"ABCD","本题考查的是设计变更程序。选项E错误，施工单位也是可以提出设计变更的，施工单位提出变更申请报监理单位审核。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]