[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113363":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113363,787,2,"多选题","下列施工组织设计编制、审核和审批工作实行分级管理制度的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工组织总设计应由总承包单位项目负责人审批",false,{"key":16,"text":17,"correct":14},"B","单位工程施工组织设计应由项目技术负责人审批",{"key":19,"text":20,"correct":21},"C","施工方案应由项目技术负责人审批",true,{"key":23,"text":24,"correct":21},"D","重大施工方案应由施工单位技术部门组织相关专家评审",{"key":26,"text":27,"correct":21},"E","专项工程施工方案应由施工单位技术负责人批准","CDE","本题考查的是施工组织设计编制要求。施工组织总设计应由总承包单位技术负责人审批；单位工程施工组织设计应由施工单位技术负责人或技术负责人授权的技术人员审批；专项工程施工组织设计（施工方 案）应由项目技术负责人审批；重大施工方案应由施工单位技术部门组织相关专家评审，施工单位技术负责人批准。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]