[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113318":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113318,787,2,"多选题","锅炉炉墙砌筑前，应有工序交接证明书，其内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","炉子中心线和控制标高的测量记录",true,{"key":16,"text":17,"correct":18},"B","锅炉安装许可通知书",false,{"key":20,"text":21,"correct":14},"C","炉体冷却装置.管道和炉壳的试压记录",{"key":23,"text":24,"correct":14},"D","上道工序成果的保护要求",{"key":26,"text":27,"correct":18},"E","锅炉监察部门阶段性检验合格记录","ACD","本题考查的是炉窑砌筑前工序交接的规定。工序交接证明书应包括下列内容：（1）炉子中心线和控制标高的测量记录以及必要的沉降观测点的测量记录；（2）隐蔽工程验收合格的证明；（3）炉体冷却装置、管道和炉壳的试压记录及焊接严密性试验合格的证明；（4）钢结构和炉内轨道等安装位置的主要尺寸的复测记录；（5）动态炉窑或炉子可动部分的试运转合格的证明；（6）炉内托砖板和锚固件等的位置、尺寸、焊接质量的检查合格的证明；（7）上道工序成果的保护要求。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]