[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113310":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113310,787,2,"多选题","下列关于伸缩缝留设规定的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用硬质绝热制品时，应预留伸缩缝",true,{"key":16,"text":17,"correct":18},"B","两固定管架间，水平管道绝热层应至少留设两道伸缩缝",false,{"key":20,"text":21,"correct":14},"C","垂直管道伸缩缝应留在法兰下面",{"key":23,"text":24,"correct":14},"D","弯头两端的直管段上应各留一道伸缩缝",{"key":26,"text":27,"correct":18},"E","保冷层两层以上时，各层伸缩缝最少应错开80mm","ACD","本题考查的是绝热层施工技术要求。选项B，两固定管架间水平管道绝热层的伸缩缝，至少应留设一道；选项E，保冷层及高温保温层的各层伸缩缝，必须错开，错开距离应大于100mm。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]