[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113297":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113297,787,2,"多选题","关于工业小型汽轮机转子安装技术要点的说法中，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","转子安装可以分为轴封安装.转子测量和转子.汽缸找中心",false,{"key":16,"text":17,"correct":14},"B","低压缸排汽口与凝汽器采用刚性中间连接段连接",{"key":19,"text":20,"correct":21},"C","转子吊装应使用有制造厂提供并具备出厂试验证书的专用横梁和吊索",true,{"key":23,"text":24,"correct":14},"D","汽轮机正式扣盖之前，应将内部零部件全部装齐后进行试扣",{"key":26,"text":27,"correct":21},"E","转子应进行轴颈圆度.圆柱度.水平度等项目的测量","CE","本题考查的是汽轮机的安装技术要求。转子安装可以分为转子吊装、转子测量和转子、汽缸找中心。凝汽器与低压缸排汽口之间的连接，采用具有伸缩性能的中间连接段，且选项B属于凝汽器安装技术要点；选项D属于气缸扣盖安装技术要点。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]