[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113289":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113289,787,2,"多选题","管道系统压力试验时对压力表的要求有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","压力表已校验并在有效期内",true,{"key":16,"text":17,"correct":18},"B","压力表精度不得低于1.5级",false,{"key":20,"text":21,"correct":18},"C","非金属管道压力表精度不得低于1.6级",{"key":23,"text":24,"correct":14},"D","压力表不少于两块",{"key":26,"text":27,"correct":14},"E","表的满刻度值应为被测压力的1.5～2倍","ADE","本题考查的是管道系统试验。试验用压力表已校验，并在有效期内，其精度不得低于1.6级，表的满刻度值应为被测压力的1.5～2倍，压力表不得少于2块。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]