[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113256":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113256,787,2,"多选题","长距离输电线路钢塔架基础施工的测量中心桩测定后，一般采用（ ）控制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","十字线法",true,{"key":16,"text":17,"correct":18},"B","水平基线",false,{"key":20,"text":21,"correct":14},"C","平行基线法",{"key":23,"text":24,"correct":18},"D","电磁波测距法",{"key":26,"text":27,"correct":18},"E","两点一线原理","AC","根据起、止点和转折点及沿途障碍物的实际情况，测设钢塔架基础中心桩，中心桩测定后，一般采用十字线法或平行基线法进行控制",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]