[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1113236,787,1,"单选题","室外排水管道安装工序是（）。2015",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分项工程",true,{"key":16,"text":17,"correct":18},"B","分部工程",false,{"key":20,"text":21,"correct":18},"C","子单位工程",{"key":23,"text":24,"correct":18},"D","单位工程","考查内容：建筑安装工程验收项目的划分。室外排水管网属于建筑给排水及供暖工程的子分部工程，它的安装工序属于分项工程。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]