[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1113230,787,1,"单选题","工业安装分部工程的质量验收应由（）负责组织。2018",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位项目负责人",true,{"key":16,"text":17,"correct":18},"B","建设单位专业技术负责人",false,{"key":20,"text":21,"correct":18},"C","监理工程师",{"key":23,"text":24,"correct":18},"D","施工单位项目负责人","分部（子分部）工程应在各分项工程验收合格的基础上，由施工单位向建设单位提出报验申请，由建设单位项目负责人（总监理工程师）组织施工单位和监理、设计等有关单位项目负责人及技术负责人进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]