[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113229,787,1,"单选题","经过返修加固处理的分项工程，外形尺寸增大仍能满足安全使用要求的可以（）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","降级验收",false,{"key":16,"text":17,"correct":18},"B","协商验收",true,{"key":20,"text":21,"correct":14},"C","鉴定验收",{"key":23,"text":24,"correct":14},"D","核算验收","本题考查的是工业安装工程质量验收评定为“不合格”时的处理办法。经返修或者加固处理的分项分部工程，虽然改变外形尺寸但仍能满足安全使用要求，可按技术方案和协商文件进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]