[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113222":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113222,787,1,"单选题","临时用电施工组织设计的主要内容不包括（）。2018",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定电源电线的位置及线路走向",false,{"key":16,"text":17,"correct":18},"B","绘制施工机械平面布置图",true,{"key":20,"text":21,"correct":14},"C","制定电气防火措施",{"key":23,"text":24,"correct":14},"D","进行负荷计算","临时用电施工组织设计的主要内容应包括：现场勘察；确定电源进线；变电所、配电室、总配电箱、分配电箱等位置及线路走向；进行负荷计算；选择变压器容量、导线截面积和电器的类型、规格；绘制电气平面图、立面图和系统图；制定安全用电技术措施和电气防火措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]