[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113220,787,1,"单选题","施工单位在电缆保护区实施爆破作业时，制定爆破施工方案应（）。201",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","邀请地方建设管理部门参与",false,{"key":16,"text":17,"correct":14},"B","报当地电力管理部门批准",{"key":19,"text":20,"correct":14},"C","及时与地下电缆管理部门沟通",{"key":22,"text":23,"correct":24},"D","邀请地下电缆管理部门派员参加",true,"爆破施工时应-邀请地下电缆管理部门参加。A选项，爆破作业不需要邀请地方建设管理部门参与；B选项，在爆破施工方案编制完成之后应报当地电力管理部门批准；C选项，在爆破作业遇到有地下电缆的情况下，应及时与点下电缆管理部门沟通，获得地下电缆埋设的准确位置。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]