[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113192,787,1,"单选题","工程竣工结算的编制依据不包括（）。2017",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工合同",false,{"key":16,"text":17,"correct":14},"B","政策性调价文件",{"key":19,"text":20,"correct":14},"C","设计变更技术核定单",{"key":22,"text":23,"correct":24},"D","招标控制价清单",true,"本题考查的是工程竣工结算。工程竣工结算的依据：（1）该工程签订的具有法律效力的施工合同和补充文件。（2）已颁发的工程造价的政策性文件和相关规定。（3）按国家预算定额及相关取费标准结算的工程，则应根据施工图预算.设计变更技术核定单和现场用工签证。（4）实行招投标的工程以中标价为结算主要依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]