[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1113191,787,1,"单选题","（2020年真题）机电工程项目成本控制的方法中，属于施工准备阶段控制的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本差异分析",false,{"key":16,"text":17,"correct":14},"B","施工成本核算",{"key":19,"text":20,"correct":21},"C","优化施工方案",true,{"key":23,"text":24,"correct":14},"D","注意工程变更","P286-291 施工准备阶段（1）制定科学先进、经济合理的施工方案。（2）根据企业下达的成本目标，以分部分项工程实物工程量为基础，结合劳动定额、材料消耗定额和技术组织措施的节约计划，在优化的施工方案的指导下编制明细而具体的成本计划，并按照部门、施工队和班组的分工进行分解。（3）间接费用的编制与落实。根据项目建设时间的长短和参加建设人数的多少，编制间接费用预算，并进行明细分解，为今后的成本控制和绩效考评提供依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]