[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1113188,787,1,"单选题","降低机电工程项目成本的合同措施不包括（）。2017.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建立成本管理责任体系",true,{"key":16,"text":17,"correct":18},"B","选择适当的合同结构模式",false,{"key":20,"text":21,"correct":18},"C","必要的合同风险防控对策",{"key":23,"text":24,"correct":18},"D","全过程的合同控制","降低项目成本的合同措施包括选用适当的合同结构模式.合同风险防控和过程的合同控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]