[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1113164,787,1,"单选题","曳引式电梯设备进场验收合格后，在驱动主机安装前的工序是（）。2015",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","土建交换检验",true,{"key":16,"text":17,"correct":18},"B","导轨安装",false,{"key":20,"text":21,"correct":18},"C","对重安装",{"key":23,"text":24,"correct":18},"D","安全部件安装","考查内容：电梯的组成。电力驱动的曳引式或强制式电梯安装子分部工程是由设备进场验收、土建交接检验，驱动主机，导轨，门系统，轿厢，对重，安全部件，悬挂装置，随行电缆，补偿装置，电气装置，整机安装验收等分项工程组成。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]