[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113143,787,1,"单选题","建筑电气装置施工中，成套配电柜安装固定后的紧后工序是（）。2011",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开箱检查",false,{"key":16,"text":17,"correct":18},"B","母线安装",true,{"key":20,"text":21,"correct":14},"C","调整试验",{"key":23,"text":24,"correct":14},"D","送电运行","查内容：电气设备.器具施工技术。成套配电柜（开关柜）安装顺序：开箱检查→二次搬运→安装固定→母线安装→二次小线连接→试验调整→送电运行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]