[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113136,787,1,"单选题","高层建筑管道工程施工程序中，管道支架安装的紧后工序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道测绘放线",false,{"key":16,"text":17,"correct":18},"B","管道元件检验",true,{"key":20,"text":21,"correct":14},"C","管道加工预制",{"key":23,"text":24,"correct":14},"D","管道元件安装","高层建筑管道工程施工的一般程序：施工准备→配合土建、预留→管道测绘放线→管道支架制作安装→管道元件检验→管道加工预制→管道安装→系统试验→防腐绝热→系统清洗→试运行→竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]