[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113134,787,1,"单选题","建筑管道配管的施工原则是（）。2011",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","大管让小管",false,{"key":16,"text":17,"correct":14},"B","风管让水管",{"key":19,"text":20,"correct":14},"C","无压管让有压管",{"key":22,"text":23,"correct":24},"D","电管让水管",true,"考查内容：给水、排水、供热及采暖工程施工程序。在编制施工组织设计时一般应考虑先难后易、先大件后小件的施工方法和遵循小管让大管、电管让水管、水管让风管、有压管让无压管的配管原则。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]