[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113131,787,1,"单选题","室内卫生器具的排水支管隐蔽前必须做（）2012",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压力试验",false,{"key":16,"text":17,"correct":18},"B","灌水试验",true,{"key":20,"text":21,"correct":14},"C","通球试验",{"key":23,"text":24,"correct":14},"D","泄露试验","考查内容：给水、排水、供热及采暖工程施工程序。隐蔽或埋地的室内排水管道在隐蔽前必须做灌水试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]