[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113130,787,1,"单选题","关于建筑管道工程系统试验的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道的压力试验应在无损检测前进行",false,{"key":16,"text":17,"correct":18},"B","通球试验的球径不小于排水管径的2\u002F3",true,{"key":20,"text":21,"correct":14},"C","高层建筑管道施工结束后应立即进行调整试验",{"key":23,"text":24,"correct":14},"D","室内埋地排水管道投用前必须做灌水试验","选项A，管道压力试验应在管道系统安装结束，经外观检查合格、管道固定牢固、无损检测和热处理合格、确保管道不再进行开孔、不再焊接作业的基础上进行；选项C，高层建筑管道应按分区、分段进行试验，合格后再按系统进行整体试验；选项D，室内隐蔽或埋地的排水管道在隐蔽前必须做灌水试验，而非使用前做灌水试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]