[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113125,787,1,"单选题","下列炉窑砌筑工序中不属于交接内容的是（）。2012",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","上道工序成果的保护要求",false,{"key":16,"text":17,"correct":18},"B","耐火材料的验收",true,{"key":20,"text":21,"correct":14},"C","炉子中心线及控制高程测量记录",{"key":23,"text":24,"correct":14},"D","炉子可动部分试运转合格证明","考查内容：炉窑砌筑工程施工程序。B选项属于施工前的工序交接。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]