[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1113115,787,1,"单选题","立式设备采用硬质或半硬质制品保温施工时，需设置（），并从该处开始自下而上拼砌。2011",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","锚固钉",false,{"key":16,"text":17,"correct":14},"B","吊架",{"key":19,"text":20,"correct":21},"C","支撑件",true,{"key":23,"text":24,"correct":14},"D","模板","考查内容：绝热工程施工技术。立式设备采用硬质或半硬质制品保温施工时，需设置支撑件，并从该处开始自下而上拼砌，然后进行环向捆扎。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]