[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113102,787,1,"单选题","自动化仪表设备安装应遵循的程序是（）2012",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","先里后外、先低后高、先轻后重",false,{"key":16,"text":17,"correct":14},"B","先外后里、先低后高、先重后轻",{"key":19,"text":20,"correct":14},"C","先外后里、先高后低、先轻后重",{"key":22,"text":23,"correct":24},"D","先里后外、先高后低、先重后轻",true,"考查内容：自动化仪表工程安装的施工程序。自动化仪表设备安装应遵循的程序是：先里后外、先高后低、先重后轻。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]