[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113092":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113092,787,1,"单选题","自动化仪表工程施工的原则是（）。2011",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先地上后地下，先两端后中间，先土建后安装，先设备后配管布线",false,{"key":16,"text":17,"correct":18},"B","先土建后安装，先两端后中间，先设备后配管布线，先地下后地上",true,{"key":20,"text":21,"correct":14},"C","先配管布线后设备，先土建后安装，先两端后中间，先地下后地上",{"key":23,"text":24,"correct":14},"D","先两端后中间，先地上后地下，先设备后配管布线，先土建后安装","考查内容：自动化仪表工程安装的施工程序。自动化仪表工程施工的原则是：先土建后安装；先地下后地上；先安装设备再配管布线；先两端（控制室、就地盘、现场和就地仪表）后中间（电缆槽、接线盒、保护管、电缆、电线和仪表管道等）。仪表设备安装应遵循的程序是：先里后外；先高后低；先重后轻。仪表调校应遵循的原则是：先取证后校验；先单校后联校；先单回路后复杂回路；先单点后网络。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]