[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113071":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113071,787,1,"单选题","锅炉系统安装程序中，水冷壁安装的紧前工序是（）。2018",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢架组合安装",false,{"key":16,"text":17,"correct":18},"B","集箱安装",true,{"key":20,"text":21,"correct":14},"C","汽包安装",{"key":23,"text":24,"correct":14},"D","省煤器安装","锅炉系统安装施工程序基础和材料验收→钢架组装及安装→汽包安装→集箱安装→水冷壁安装→空气预热器安装→省煤器安装→低温过热器安装→高温过热器安装→刚性梁安装→本体管道安装→阀门及吹灰设备安装→燃烧器、油枪、点火枪的安装→烟道、风道的安装→炉墙施工→水压试验→风压试验→烘炉、煮炉、蒸汽吹扫→试运行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]