[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113069,787,1,"单选题","电站锅炉本体受热面组合安装时，设备清点检查的紧后工序是（）。2013",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","找正划线",false,{"key":16,"text":17,"correct":14},"B","管子就位",{"key":19,"text":20,"correct":14},"C","对口焊接",{"key":22,"text":23,"correct":24},"D","通球试验",true,"考查内容：动力设备安装工程施工技术。锅炉本体受热面安装一般程序：设备清点检查一通球试验一联箱找正划线一管子就位对口和焊接。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]