[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1113063,787,1,"单选题","管道工程施工程序中管道安装的紧后工序是（）。2012",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道系统防腐",false,{"key":16,"text":17,"correct":18},"B","管道系统检验",true,{"key":20,"text":21,"correct":14},"C","管道系统绝热",{"key":23,"text":24,"correct":14},"D","管道系统清洗","考查内容：管道工程施工程序。管道工程的一般施工程序是：施工准备（技术、人员、机具、材料、现场）→配合土建预留、预埋、测量→管道、支架预制→附件、法兰加工、检验→管段预制→管道安装→管道系统检验→管道系统试验→防腐绝热→系统清洗→资料汇总、绘制竣工图→竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]