[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113030,787,1,"单选题","地下管线工程回填前，不需要测量的项目是（ ）。2019.3",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管线起点坐标",false,{"key":16,"text":17,"correct":14},"B","窨井位置坐标",{"key":19,"text":20,"correct":14},"C","管线顶端标高",{"key":22,"text":23,"correct":24},"D","管线中心标高",true,"地下管线工程测量：地下管线工程测量必须在回填前，测量出起、止点，窨井的坐标和管顶标高。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]