[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113018":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113018,787,1,"单选题","在厂房不大的情况，设备安装过程中，标高起算点宜（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","每台设备各设置一个",false,{"key":16,"text":17,"correct":14},"B","不同类别设备分别设置",{"key":19,"text":20,"correct":14},"C","相关联设备设置一个",{"key":22,"text":23,"correct":24},"D","所有设备设置一个",true,"设备安装过程中，测量时应注意：最好使用一个水准点作为高程起算点。当厂房较大时，可以增设水准点，但其观测精度应提高。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]