[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113017":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1113017,787,1,"单选题","长距离输电线路钢塔架基础施工中，大跨越档距之间测量通常采用（）2010",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","十字线法",false,{"key":16,"text":17,"correct":14},"B","平行基线法",{"key":19,"text":20,"correct":21},"C","电磁波测距法",true,{"key":23,"text":24,"correct":14},"D","钢尺量距法","考查内容：长距离输电线路钢塔架、铁塔、基础施工的测量。中心桩测定后，一般采用十字线法或平行基线法进行控制。在大跨越档距之间，通常采用电磁波测距法或解析法测量。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]