[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1113015,787,1,"单选题","安装标高基准点一般设置在设备基础（）。2013",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","最高点",false,{"key":16,"text":17,"correct":14},"B","最低点",{"key":19,"text":20,"correct":14},"C","中心标板上",{"key":22,"text":23,"correct":24},"D","边缘附近",true,"考查内容：机电工程测量的方法。标高基准点一般埋设在基础边缘且便于观测的位置。标高基准点一般有两种：一种是简单的标高基准点；另一种是预埋标高基准点。简单的标高基准点一般作为独立设备安装的基准点；预埋标高基准点主要用于连续生产线上的设备在安装时使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]