[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112965,787,1,"单选题","分项工程可由一个或若干个（ ）组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","子分项",false,{"key":16,"text":17,"correct":14},"B","子项目",{"key":19,"text":20,"correct":21},"C","检验批",true,{"key":23,"text":24,"correct":14},"D","检查批","2020版教材P363 3、分项工程、检验批的划分（1）分项工程可由一个或若干个检验批组成。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]