[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112956,787,1,"单选题","建筑安装工程质量验收评定是施工单位进行（ ）的反映。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量控制结果",true,{"key":16,"text":17,"correct":18},"B","质量管理绩效",false,{"key":20,"text":21,"correct":18},"C","质量提高目标",{"key":23,"text":24,"correct":18},"D","质量创新成果","2020版教材P364 一、建筑安装工程质量验收程序建筑安装工程质量验收是施工单位进行质量控制结果的反映，也是竣工验收确认工程质量的主要方法和手段。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]