[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112949,787,1,"单选题","分包单位对承包的项目进行验收时，（ ）参加。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质监部门",false,{"key":16,"text":17,"correct":14},"B","供应商",{"key":19,"text":20,"correct":21},"C","总包单位",true,{"key":23,"text":24,"correct":14},"D","设计单位","2020版教材P362 总承包单位应对分包工程质量全面负责，并应由总承包单位报验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]