[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112897,787,1,"单选题","临时用电的准用程序中包括：①协助业主向当地电业部门申报用电方案；②经电业部门检查、验收和试验，同意送电后送电开通；③对施工项目进行检查、验收，向电业部门提供相关资料，申请送电；④进行临时用电设备、材料的采购和施工。其正确的准用程序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①→③→④→②",false,{"key":16,"text":17,"correct":14},"B","③→④→①→②",{"key":19,"text":20,"correct":21},"C","①→④→③→②",true,{"key":23,"text":24,"correct":14},"D","④→③→①→②","2020版教材P340 临时用电的准用程序：1）施工单位应根据国家有关标准、规范和施工现场的实际负荷情况，编制施工现场“临时用电施工组织设计”，并协助业主向当地电业部门申报用电方案。2）按照电业部门批复的方案及《施工现场临时用电安全技术规范》进行临时用电设备、材料的采购和施工。3）对临时用电施工项目进行检查、验收，并向供电部门提供相关资料，申请送电。4）经供电部门检查、验收和试验，同意送电后送电开通。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]